Window replacement in Berwick, step by step, day by day.

Accepted quote to finished job is 5 to 8 weeks, and nearly all of that is factory time. The crew is on site 1 to 3 days for a typical 10 to 12 opening Casey house. Each standard opening is out and sealed in 1 to 3 hours, a sliding door takes 3 to 5, and your house is never open to the weather in more than one place at a time.

The timeline

Every stage, how long it takes, and what you have to do.

Timings below are for a single-storey Berwick, Narre Warren or Cranbourne house with 10 to 12 openings and one sliding door, all in their existing structural openings.

Stage How long What happens What you need to do
1. Free measure and quote 45-90 min on site, quote in 7 days Every opening measured twice, elevations and wind exposure noted, glazing options priced both ways Be home, unlock side gates, say which rooms bother you
2. Order and deposit Same week Colour, glazing, hardware and screen type locked in and the order released to the factory Choose the powder coat colour, sign the scope, pay the deposit
3. Check measure 30-45 min, 1-2 weeks later Second measure against the shop drawings before anything is cut. This is where errors get caught 15 minutes of access, confirm handle sides and opening directions
4. Manufacture 4-6 weeks aluminium, 8-12 timber or uPVC Frames extruded, powder coated, glazed and assembled. Nothing happens at your house Book leave or a work-from-home day for the install week
5. Delivery and set-up 7am to 8am, day 1 Units unloaded and stood against the wall, floors covered, dust screens hung, power leads run Clear the driveway, keep pets inside, gates unlocked
6. Strip-out and fit, per opening 1-3 hours each Sash and glass out, frame cut free, opening cleaned, new frame packed, plumbed, levelled, fixed and flashed Stay out of that room, keep kids and pets away from glass
7. Sliding or stacker door 3-5 hours Heavier frame, sill set in a bed of sealant, tracks levelled, panels hung and adjusted, threshold waterproofed Clear the alfresco and the internal traffic path for the day
8. Make-good and sealing Last afternoon Reveals patched, architraves refitted, backing rod and neutral-cure silicone tooled inside and out Nothing. Do not touch a fresh bead for 24 hours
9. Clean-up and handover 30-60 min Vacuum, glass cleaned, screens fitted, every sash and lock demonstrated, warranty and compliance paperwork handed over Walk every opening with the installer before you sign off
10. Painting 3-7 days after Patched reveals and architraves are painted once the filler and sealant have cured Your painter, or ours. Do not paint over fresh silicone

Two-storey work adds a scaffold day at each end. Wet weather stops new openings being cut, not the fit-off. Call (03) 9022 6418 if you need a date locked around school holidays.

Before the crew arrives

Prepare-for-the-crew checklist.

Tick these off the week before. Your ticks are saved in this browser, and the print button gives you a clean copy for the fridge.

Inside, the week before

Outside and access

People, pets and the working day

Paperwork and handover

Stop the job if you see these

Want the install day mapped out for your house?

We give you the room order and the finish time before we start, so you can plan the week around it.

On the day

Access, noise, dust and the things nobody warns you about.

Access and parking. We need the driveway from 7am for a ute and a trailer, and a clear path from there to each elevation. New estate streets through Clyde North, Berwick Waters and parts of Cranbourne East are narrow with kerbside parking on both sides, so tell us at the measure if the truck will not fit past a parked car. On the older Doveton and Endeavour Hills blocks the usual obstacle is a side gate too narrow for a 2.4 metre sliding panel, which we would rather find out at the measure than on install morning.

Power and water. A standard 10 amp external power point runs everything we use. If there is no external outlet we run a lead from inside, which means a door propped for the day. An outside tap is used for wet-cutting and clean-up. Neither is a deal breaker, but both are worth mentioning up front.

Noise. The genuinely loud parts are short. Cutting an old frame free with a multi-tool or grinder takes 10 to 20 minutes per opening and drilling the fixings adds a few minutes. Victorian residential noise rules set the hours for power tools on domestic premises: not before 7am or after 8pm Monday to Friday, and not before 9am or after 8pm on weekends and public holidays. We work inside those hours, and we do not do out-of-hours installs.

Dust and smell. Brick, render and mortar dust contains crystalline silica, so cutting is done with on-tool extraction or wet-cut wherever possible, and dust screens go up across doorways. Even done properly, expect a fine film within two metres of each opening and a bit of grit on the floor until the final vacuum. Neutral-cure silicone has a mild odour for a few hours and is essentially gone by the next morning. If anyone in the house has a respiratory condition, tell us and we will schedule their room for a day they can be out.

Pets, kids and working from home. An opening sits empty for an hour or two, gates get propped and there is glass on the ground. Dogs go to a run or to day care, cats go in a closed room with a sign on the door. Working from home is completely normal: ask for the room order and book calls for before the first cut or after about 3pm when the day moves to sealing and clean-up.

Weather. We fit opening by opening rather than stripping the house out, so the house is never widely exposed. In steady rain we stop cutting new openings and finish what is already out, which is how a two-day job becomes a three-day job in a wet week. Sustained wind over about 40km/h stops us handling large glass on a ladder or a scaffold, for obvious reasons. We will call you the afternoon before if the forecast is going to move the date.

At the end

What a clean site looks like, and where the waste goes.

A finished job means every sash operates with one hand, every lock engages, screens are fitted, the internal and external sealant beads are tooled evenly with no smears on the brickwork, the reveals are patched flat and ready for paint, the glass is clean both sides, the floors are vacuumed and there is nothing left in the garden beds. Offcuts, packaging film, old screens and the old frames all leave with us the same day. Walk every opening with the installer before the final payment and operate everything yourself: it is much easier to adjust a stiff sash while the crew is still standing there.

The old aluminium frames go to a scrap metal recycler after the glass is stripped out, which is exactly why removal and disposal is included in our price rather than added as a line item. Toughened and laminated glass cannot go in a kerbside recycling bin and goes to a transfer station as hard waste. Old timber sashes from pre-1970 houses may carry lead-based paint, so they are bagged and handled separately rather than cut or sanded on site. If you would rather keep a couple of old sashes for a shed or a greenhouse, say so at the measure and we will leave them.

The honest bit. Two things we will not do. We will not open a wall in sustained rain to keep a schedule, even if it costs us the day, because a wet frame cavity is a mould problem you will be living with later. And we will not install into a tenanted property without the tenant's written agreement to the dates, because a job worked around an unhappy household ends badly for everyone. If you are chasing us because a window is broken right now rather than worn out, the faster route is often an insurance claim and a temporary board-up, which we cover on the window insurance claims page. If you are weighing up doing part of it yourself, the honest split of what is a weekend and what is not is on the DIY versus professional page, and once the job is done the aftercare routine is on the maintenance page.

Get a price

Book the measure and we will map out your install week.

Free on-site measure, written quote within 7 days, and a room-by-room schedule before the first cut so you know exactly which day is loud.

We reply within 1 business day. Free, no obligation.

Install day questions

What Casey homeowners ask before the crew arrives.

How long does window replacement take on a Berwick house?
From accepted quote to finished job is normally 5 to 8 weeks, and almost all of that is factory time. Aluminium runs 4 to 6 weeks in manufacture and timber or imported uPVC runs 8 to 12. The crew is only on site for 1 to 3 days on a typical 10 to 12 opening house. Each standard opening takes 1 to 3 hours from strip-out to sealed, and a sliding or stacker door takes 3 to 5 hours.
Is my house open to the weather during the install?
Only one opening at a time, and only for the 1 to 3 hours it takes to fit that window. We work opening by opening rather than stripping the whole house out, so the house is never wide open. If steady rain sets in we stop opening new holes and finish what is already out, which is why a wet week can push a two-day job to three.
How much noise and dust does window replacement make?
The loud parts are short. Cutting the old frame out with a multi-tool or grinder is 10 to 20 minutes per opening, and drilling the fixings is a few minutes more. Under Victorian residential noise rules, power tools on a domestic site should not run before 7am or after 8pm on weekdays, or before 9am on weekends and public holidays. Brick and render dust is controlled with on-tool extraction and drop sheets, but expect a fine film within about two metres of each opening.
What do I need to move before the window crew arrives?
Curtains, blinds and their tracks, internal security screens, anything hanging on the wall within about a metre of the opening, and all furniture pulled 2 metres clear. Outside, cut back shrubs and move pots so there is a working platform of about 1.5 metres along the wall. Doing that yourself the night before saves the crew roughly an hour a room and keeps the job on schedule.
What happens to the old windows and glass?
The aluminium frames are stripped of glass and sent to a scrap metal recycler, which is why disposal is included rather than charged as an extra. Toughened and laminated glass cannot go in a kerbside bin and goes to the transfer station as hard waste, and old timber sashes with lead-era paint are handled separately. Removal and disposal on a typical job is worth $40 to $120 per opening if you were paying for it yourself.
Can I stay home and keep working during a window install?
Yes, and most people do. Pick a room we are not working in that day and ask for the schedule so you know when the noisy 20 minutes hits each opening. Book calls for early morning before the first cut or after about 3pm when we move to sealing and clean-up. If you take video calls all day, it is worth working elsewhere on the single day we do the living areas.